top of page

PROJECTS

Apex Rail has been providing civil and rail services across Victoria since 2014.

In that time, we have successfully completed a number of extensive projects from Track Maintenance and Construction, Bulk Earthworks, Drainage Installation, Bridge Structures, Culvert Replacements and Subgrade Stabilisation Works.

We are currently pre-approved subcontractors for V/Line and Metro Trains Melbourne (MTM) and have worked as part of major Alliance and Joint Venture teams and well as directly with asset owners to deliver works across both the Metro and Regional rail networks.

SHEPARTON CORRIDOR UPGRADE PROJECT

Project Start/Finish Date: August 2021 to February 2022​

Client: Coleman Rail

​​​

Murchison East Loop

Earthworks – Strip Topsoil and Organic material, Bulk Earthworks and Subgrade Preparation, Track Formation Works.

Drainage - Construct and installation of new formation and access track cess drains. Drainage was installed across the Murchison Passing Loop.

 

Stabling Yard, Mainline Slew and Turn out

Earthworks - Strip Topsoil, Bulk Earthworks – Cut to Fill and load out of excess material, Lime stabilization, Place and compact – Structural Fill, Capping Bottom Ballast.

Drainage - RCP Pipe, cess Drainage, Cross Track Culverts, Subsoil Drainage, Intertrack Drainage.

Piling -Bored Piling works (including placement of Pile cage & rag bolt sets, Services Gantry Piles, Light pole and CCTV piles, Amenities Building Slab and footings, Storage Building slab and footings.

MELBOURNE WATER SCHEME PIPE CROSSING RAIL -

Thornhill Park, Stage 29

Spiire

 

28th to 31st December 2020

 

  • ​Installation of approximately 35m of 1500dia drainage Melbourne Water Culvert Crossing the Ballarat V/Line Rail line and extending into the subdivision of Thornhill Park during Occupation (Christmas/New Year 2020)

WESTERN PROGRAM ALLIANCE (WPA) -

Wyndham Vale Stabling Yard

McConnell Dowell Constructors (Aust) Pty Ltd - Ongoing

 

Feb 2019 to April 2019

 

Crossover Pre-Build and Installation

CSR Civils

 

  • Pre-building of 4 no. 1:15 VCA Crossovers

  • Installation of 4 no. 1:15 VCA Crossovers during Occupation (Easter 2019)

  • CSR installation

BALLARAT LINE UPGRADE PROJECT  (BLU)

Lend Lease Coleman Rail Joint Venture 

 

April 2018 to Jan 2019

 

CSR, Plant Hire + Maddingley Stabling Yard Track & Civils

 

  • 8,000m of CSR installation

  • 20,000m3 bulk excavation

  • 3,500m3 embankment widening

  • 2,000lm of RCP and slotted drainage installation

  • 50 pits installed

  • 11,500m2 of lime stabilization, formation and capping

  • 1200mm dia culvert extensions

TIMBER CULVERT REPLACEMENT -

Minyip & Hopetoun

V/Line Pty Ltd

 

May 2018 to July 2018

 

Minyip and Hopetoun

 

  • Box culvert installation under Main St Minyip

  • Telstra lowering

  • Water main re-routing

  • Box culvert installation under 3no. tracks at Hopetoun under occupation

MURRAY BASIN RAIL PROJECT

McConnell Dowell Martinus Joint Venture (MMJV) 

 

July 2017 to March 2018

 

Junction Works

  • Construction and gauge conversion of 15 no turnouts

  • Formation and Capping Construction

  • Replacement of 2,000 sleepers

  • 5,000m of Gauge Conversion 

  • 2 x Level Crossing Reconstructions

  • Wet hire plant

bottom of page